Assignment No 2 Submitted by: Shubham Ashok Salunke (200535900) Answers: 1.(PV) Planned value= $1000+$1000+$1000=$3000. 2.(EV) Earned value= $1000+$1000+$500+$750=$3250. 3.(AC) Actual Cost= $1000+$900+$600+$600=$3100. 4.(BAC) Budget at completion= $1000 x 4=$4000. 5.(CV) Cost Variance = EV- AC = $3250 - $3100=150, Under budget. 6.(CPI) Cost Performance Index = EV/AC = 3250/3100=1.05, Good. 7.(SV) Schedule Variance = EV - PV = $3250 - $3000=$250, Ahead of schedule. 8.(SPI) Schedule Performance Index = EV/PV = $3250/ $3000 =1.08, Good. 9.(EAC) Estimate At Completion = AC+(BAC - EV) = $3100 + ($4000 - $3250) =$3850. 10. (ETC) Estimate to Complete = EAC - AC = $3850 - $3100 =$750. 11. (VAC) Variance at completion = BAC - EAC = $4000 - $ 3850 =$150
Sr No.What is:CalculationsResultsReview 1(PV) Planned value$1000+$1000+$1000$3000 2(EV) Earned value$1000+$1000+$500+$750$3250 3(AC) Actual Cost$1000+$900+$600+$600$3100 4(BAC) Budget at completion$1000 x 4$4000 5(CV) Cost VarianceEV- AC = $3250 - $3100$150Under budget 6(CPI) Cost Performance IndexEV/AC = 3250/31501.05Good 7(SV) Schedule VarianceEV - PV = $3250 - $3000$250Ahead of schedule 8(SPI) Schedule Performance IndexEV/PV = $3250/ $30001.08Good 9(EAC) Estimate At CompletionAC+(BAC - EV) = $3100 + ($4000 - $3250)$3850 10(ETC) Estimate to CompleteEAC - AC = $3850 - $3100$750 11(VAC) Variance at completionBAC - EAC = $4000 - $ 3850$150
Expert's Answer
Chat with our Experts
Want to contact us directly? No Problem. We are always here for you
Your future, our responsibilty submit your task on time.
Order NowGet Online
Assignment Help Services