SECTION B – REQUIRED KNOWLEDGE
Assessment Task 2 - Written Questions
Instructions
You are required to provide a satisfactory response to each question below to complete this assessment.
Question 1
How would you describe a building defect?
Question 2
What are the two categories of defects and provide an example of each?
Question 3
What do the following headings mean in a defects report?
Question 4
List six (6) examples of Essential Safety Measures (ESM) that you would require an Engineers Certificate of Compliance for.
Question 5
- Describe a method that can be used to estimate building rectification costs
- When would it be preferable to demolish an existing building rather than renovate it?
Question 6
What are six (6) key benefits of a feasibility study?
Question 7
What do the following terms used in feasibility studies mean?
Question 8
What are three (3) typical design deliverables in a project brief?
Question 9
What is the difference between prescriptive requirements and performance requirements in a design brief?
Question 10
Name five (5) types of consultants you could use to assess site conditions.
Question 11
What is the definition of an “opinion of probable cost”?
Question 12
What are the components of an opinion of probable cost?
Question 13
What should client approval of final design documentation include:
Question 14
When is ‘planning approval’ required for a project?
Question 15
List seven (7) key steps in the process of obtaining ‘planning approval’.
Question 16
When should an application be lodged with the Municipal Council to extend a planning permit?
Question 17
What three (3) things must VCAT do to offer a ‘fair hearing’ to all parties to a case?
Question 18
Name five (5) common mistakes in the contract documentation for a project.
Question 19
Name any five (5) key aspects to be monitored during construction.
Question 20
Name five (5) typical examples of events outside the builder’s control.
Question 21
List five (5) examples of the information that needs to be submitted in a request for a variation?
Question 22
What is the purpose of a progress schedule?
Question 23
List five (5) examples the various legal reports and supporting documents that may be required in an attempt to settle a legal dispute:
Question 24
Name two (2) examples of an ‘alternative dispute resolution’ method?
Question 25
What is the purpose of a ‘Probity Plan’ in a commercial agreement?
Question 26
Provide three (3) examples of circumstances that may arise during a project requiring legal interpretation.
Question 27
What is one of the most important attributes of an expert witness?
Breathe a Sign of Relief with our Academic Assistance: Get instant help, 100% personalized and accurate solutions that make your study life better.
Expert's Answer
Chat with our Experts
Want to contact us directly? No Problem. We are always here for you
Your future, our responsibilty submit your task on time.
Order NowGet Online
Assignment Help Services